Assistant Manager - Analytics And Business Excellence
Current-Objective:- Manpower Optimization in Captive Power Plant ,Structure Steel Department, Steel Melting Shop ,Wire Rod Mill Result- Manpower Optimized by 13% and productivity increases.-Objective-Optimization of HMV (Heavy Moving Vehicle) across the plant using MOST and Queueing theory Result- HMV reduced from 273 to 257 which increase productivity.-Objective- Finalizing the contractual Manpower across the plant as per 8 hrs shift and 12 hrs shift. Result- Optimizing the cost and enhance the productivity.-Generating report of KPI related to Raw material , Work In Process & Final Product and giving Insights to the HIgher Management Authority.- Interpersonal skill to communicate with Higher Management and implementing changes on the shop floor.