Principal
CurrentLaGuardia Airport: Terminal C Airfield Reconfiguration Project, Queens, NYRecruited to spearhead the site wide management of existing as well as new Landside and Airside Construction of Delta’s $4 billion Terminal C Project.Key Accomplishments:• Successfully managed and delivered _ worth of new Arrivals and Departures Roadway network for the new terminal.• Supervised and managed Airside Construction and Phasing in coordination with Flight Operations• Provided solutions to complex phasing requirements needed to build new infrastructure while keeping the existing infrastructure fully operational. • Facilitated constant communication amongst the key stakeholders about challenges, solutions, goals, and opportunities• Coordinated extensively with contractors, designers, executives to install $50 Million worth of Utilities such as Storm Lines, Water Lines, Sanitary Lines, 5kV and 27kV Lines, Hydrant Fuel System, Communication Lines and so on.