Site Agent
CurrentI'm extremely proud to have played a key role in the successful delivery of two HS2 bridge structures during the Summer of 2023. The first was the highly commended Fulfen Wood reinforced concrete box bridge, which was cast on site and installed during a 9-day blockade of the West Coast Mainline. The Fulfen Wood bridge weighed 6200te and was the heaviest bridge structure to be installed in the UK using Self Propelled Modular Transporters (SPMTs).The second bridge was Streethay, which was installed during a 72 day blockade of the South Staffordshire Line. This was a 2600te reinforced concrete bridge deck supported on Secant piles and capping beams.Both schemes required the removal and reinstatement of the railway lines.