Project Manager
Spalding, Lincolnshire U.K
• Supported the senior project manager in performance of the Spalding Energy Project in the United Kingdom. The Spalding Energy was a 860 MW LSTK project combined cycle plant comprising two GE 9FA combustion turbine generators (CTG’s), two NEM three-pressure reheat heat recovery steam generators (HRSG’s) and a Hitachi dual-admission reheat steam turbine generator (STG). • Principal duties included overall schedule development, management of the design engineering, management of construction subcontract package development, and oversight of the fabrication and delivery of the Hitachi steam turbine, the critical path of the overall project schedule. • Engineering completed on schedule, the steam turbine was delivered five (5) weeks ahead of guarantee date, subcontractor requests for extra’s were less than 3.0%, the project completed one and a half (1.5) months ahead of the guarantee date, and as-booked gross margin (GM) significantly improved.