Lead Coker And Sulfur Planner
Current- Fixed Equipment Planner
- Accountable for 40% of the workload put to schedule as one of five planners
- Collaborate with Process Mechanical Coordinator to efficiently allocate resources to priority repairs within the Coker/Sulfur unit
- Communicate with Execution Superintendent to maximize utilization of workforce and minimize cost by resourcefully delegating workload to ExxonMobil and contract companies
- Independently maintain Coker/Sulfur unit backlog by placing, on average, 48 jobs per month to the schedule
- Planned 578 work orders, 38,563 hours, and 231 full time equivalents in the year 2023