Construction Manager
CurrentED/2018/04Trunk Road T2Leading 2 teams with 8 engineers and 7 supervisorsConstruction of west ventilation building:Design coordination, methodolgoy, cost saving designMaster programming including cost estimation and cost control.Liaision with other main contractorsPrepartion of VO to clientTypical ELS construction methodolgoyBottom up constrcutionABWF worksConstruction of footbridgeDesign coordination, methodolgoy, cost saving designMaster programming including cost estimation and cost control.Piling worksPost tensioning of 130lm bridgeFinshing works, glass canopy, RC structureCurrent:MTRC 1201Leading a team of 6 engineers and supervising;D-wall constructionSite setup and clearanceH-piling constructionMethodolgoy study of Tung Chung West station RC including semi top down constructionMaster program preparation and detail cost estimation