Civil Engineering Consultant
Current- Client: Queensland Urban UtilitiesContract Manager/Superintendents Rep (Major Projects) March 2017 – March 2022
- TBM, HDD and open excavation for trunk sewer and water main augmentations
- Construction of Sewer Treatment Plant, Pumping Stations and Rising MainsClient: SunWaterConstruction Manager/Superintendents Rep (Major Projects) May 2016 – December 2016Stage 1 of the spillway safety improvement.
- Bulk earthworks for access and working platform
- DHH drilling and installation of anchor bars
- Replacement of spillway drainage system