Summer Engineering Intern
Department: Technical Team (Method)Project: Trunk Road T2 and Infrastructure Works for Developments at the Former South Apron-Investigated the discrepant level difference at the interface between cross passages and parapets as well as prepared the CAD drawings to show the constraints-Investigated the Internal Slab Structure Gantry (ISSG) dismantling area and last OHVD slabs installation area-Assisted in designing the method and brackets required for installing overhead ventilation ducts (OHVD) slabs at the interface between the Kai Tak sub-sea section and the Cha Kwo Ling section-Compared the as-built chainage of OHVD slabs with the theoretical chainage as well as investigated the discrepancy of chainage on site