Road Maintenance Supervisor
CurrentEAR1TH WORKSAt; - BACK FILLING for buildings to allow the CONSTRUCTION works to start at GC-31. for subbase layers for the primary and main roads OSPL & ISPL.- GRADING , LEVELING for tanks inside , entrances , under pipe sleeperes and road shoulders- APPLYING WORKS for roads [asphalt] , for bundwalls + swales and slope protections [sandmix] . for shellers yards + under pipe racks sleeperes [gravel] .- INSTALLATION WORKS HSF high security fence. LSF low security fence. BUND WALL for (TK(1,2,3,4,5a,5b,6a,6b,7,8,&13a,13b). LIGHT POLE bases. DUCT Banks. CULVERTs.- RESPONSIBILITY TAKING AS A PERMIT HOLDER /WSS/ FOR THE BLDGS, TV GAS SECURITY EQUIPMENT MAINTENANCE CONTROL SUBSTATION