Project Manager
CurrentProject as a Project Manager (1). Fountainhead School, Kukni Village, Surat, GujaratProject :- Renovation of DP-wing (fast-track Project)Planned Project Duration:- 66 daysActual Project Duration:- 67 daysDesigner/Architect:- EDI (banglore)Contractor:- 4 wall street interiorsTotal Project Area:- 13,732 Sq.ftChallenging Aspects of the project:- (1). Timeline - Hardly 2 Months only(2). Screeding & self leveling treatment on the existing Kota stone flooring.(3). Existing un-even RCC surfaces which are kept exposed(2). Surat Textile Bourse, BRC campus, Udhna, Surat.Project Area :- 2,70,000 sqft Total Average Manpower deployed daily:- 130Daily Average Concrete Pouring :- 70 CUM.Delivering quality work with tremendous speed.Challenge:- - Double height of Floor- Project Management - weather conditions - facing limitations in person's single shift stretch