Engineer
CurrentI have been working on projects primarily for the San Francisco Public Utilities Commission as the General Contractor. Projects include the San Andreas Pipeline #2 (SAPL 2) replacement as well as two strategic Ground Water Recovery Projects. The SAPL 2 project consists of demolition of approx 5,000ft of aging 54” diameter pipeline and installation of a new 54” butt welded steel pipe using open cut methods. This project also included approx 1,500ft of slip lining a new 42'' butt welded steel pipe inside sections of the existing 54'' pipe. The Groundwater Projects consists of construction of 12ea well water pumping stations with chemical treatment processes and extensive SCADA integration as well as approx 40,000ft of discharge and utility pipelines installed by both open trench and trenchless methods.