Project Engineering Intern
• Involved in project of converting 3 mechanically vented rooms, including plant room, switch room and transformer room into air-conditioned room, carried out heat load calculations, equipment selection, and designing of ducting layout and duct sizing.• Involved in project of moving plant room equipment, including 1 zero purge dryer, and 1 air compressor. Developed a detailed equipment movement plan, liaised with contractors to receive quotation for on-site modifications and movement of equipment. Navigated site constraints and scheduling challenges.• Performed a thorough comparison of 2 chiller brands to identify the most cost-effective and reliable replacement for existing units. Assessed criteria including financial impact, energy efficiency, and risk of downtime. Provided the owners of the building with a recommendation which they approved.