Deputy Manager
CurrentOverall Execution successful execution of Turbine Generator Island package for 2x800MW Darlipali Super Thermal Power Project, Orissa for NTPC Limited. Preparation of Techno-commercial bid to Execution stage of NTPC 2x 800 MW Darlipali Project. Co-ordination with NTPC and Erection contractor for Erection & Commissioning activities at site,Monitoring and coordinating the project progress, Finalization of Work Breakdown Structure and Schedules (L2, L3 & L4) with Client and Erection Contractor.Co-ordination with Site and Production team for package supply progress and follow up for short supplies and SUI’s as per project progress requirement.Participated in (Contract Review Meeting/ Site Review Meetings) for Erection and commissioning progress of TG & Auxiliary package as per Project Schedule.