Site Engineer
• Hyundai Engineering & Construction Co., Ltd
Four Seasons Hotel @ Nile Plaza With A Total Budget 600 Million L.E.
Responsibility : Site Eng. For concrete structure works & finishing works. Finishing Items : Block, Plaster, Gypsum, Vinyl wall covering, Gypsum partitions, Wood cladding, Stone cladding, GRG, and Fabric for walls. Acoustic tile, gypsum board , and sound rated for ceiling. Raised floor, Floating slabs, Vinyl tiles, Stone, Carpet, Poly yorthan floors, Epoxy, Wooden, and Deferent type of Water proofing system for floors. For doors types, Pressed steel doors, wooden doors, Glass doors, and Roller shutters. All the building is 2 hours FIRE RATED Wall paper installation All wooden works in busness suit area ( installation & inspection) All types of cornices,skirting, Darpery pocket,all types of cladding, Sub frames, door frames, door panel. All final snag works in business suit area.