Area Construction Manager
Singapore
The ECC (Ethylene Cracker Debottlenecking) project contains a portfolio of upgrade projects to be completed during the ECC turnaround 2014, Bukom Island - Singapore. As the Area Construction Manager (hot section including the crackers, approximately 1/3 of the total project scope), I have been in charge of the completion of the scope safely, on cost & schedule. The hot-section scope includes the installation of 2 new cracking furnaces, 2 new 260T heatexchangers, expansion of pumping capacity and installation of large volume of piping with ~ 500 tie-ins. Modification to the Gasoline Fractionator and Quench Water column as well as various other smaller equipment modifications.