Oliver Long

Oliver Long Email and Phone Number

Operations Director @ Keltbray Group
Flitwick, GB
Oliver Long's Location
Flitwick, England, United Kingdom, United Kingdom
Oliver Long's Contact Details

Oliver Long personal email

n/a
About Oliver Long

An experienced senior manager with a vast understanding of the management of health and safety, environmental matters, planning and programming, temporary works, estimating, labour plant and material ordering, reporting to client and main company directors, selection of and management of subcontractors, demolition (e.g. within a city centre environment ranging from low, mid to high rise, façade retention, soft strip, asbestos removal, cut/carve and temporary works) recent experience includes Rail projects (Crossrail & Network Rail) and groundworks (e.g. basement excavations, temporary works, bulk excavation, drainage, road construction, reinforced concrete works, underpinning and ground stabilisation)All gained through working in the construction industry since the late 1980s, starting as an engineers assistant and progressing through the management levels (e.g. Site Engineer, Project Engineer, Site Manager, Project Manager, Construction Manager, Contracts Manager) to my current position of Operations Director.Specialities: Superstructure & Substructure Demolition, Façade retention demolition, party-wall propping, basement propping, pile enabling, groundworks with deep basement excavations.Liaison with local authorities (City of London, Islington, Westminster City Council, Transport for London, Birmingham City Council and Milton Keynes Council)

Oliver Long's Current Company Details
Keltbray Group

Keltbray Group

View
Operations Director
Flitwick, GB
Website:
keltbray.com
Employees:
1405
Oliver Long Work Experience Details
  • Keltbray Group
    Operations Director
    Keltbray Group
    Flitwick, Gb
  • Keltbray
    Curzon Street Pre Main Works Package - Hs2 Birmingham
    Keltbray May 2023 - Present
    Hs2, Curzon Street, Birmingham, England, United Kingdom
    Member of the Keltbray project team undertaking the Pre-Main Works package for Mace Dragados JV& HS2 at Curzon Street, Birmingham. The packages include the following scope: General excavation to remove the existing weathering layer, Construction of piling platform, Construction of 86 lm of contig piles adjacent to the RBS NR line, Supply, excavation and construction of the below-ground storm and foul drainage, Construction of a 500 lm concrete haul road, Excavation and removal of redundant service berms, Excavation of the “Berm of Dirt” adjacent to the RBS NR line, Construction of the Green Road extension, Dismantle of existing site hoardings following the closure of New Canal Street, Construction of a concrete capping beam over the contig piles, Ground investigations associated with the proposed welfare facility.
  • Keltbray
    The Gables & Mellish Court Demolition
    Keltbray Jul 2022 - Present
    Milton Keynes, England, United Kingdom
    Member of the Keltbray project team undertaking the Demolition of “The Gables”, an 11-storey residential block and “Mellish Court”, an 18-story residential block for Milton Keynes Council. The packages include the following scope: Securing the site boundary, Establishing site welfare, R&D Asbestos surveys, Soft Strip, scaffolding to both blocks, installation of demolition associated temporary works, structural demolition and foundation removal.
  • Keltbray
    Maria Fidelis Accommodation Package - Hs2 Euston
    Keltbray Oct 2021 - Present
    Hs2 Euston
    Member of the Keltbray project team undertaking the Piling & Groundworks package for Mace Dragados JV& HS2 at Euston. The packages include the following scope: Installation & Testing of Insitu HIPER pile. Construction of piling platform, Construction of 35No Insitu & 5No HIPER piles, Design and installation of the ground source heat pump system between the HIPER piles and the service riser, supply, excavation and construction of the below-ground storm and foul drainage, construction of a ground floor concrete slab, single-story steel frame structure, excavation and installation of service ducting, construction of a UKPN substation, construction of blockwork to ground floor workshops, permeable paving to external areas.
  • Keltbray Group
    Operations Director
    Keltbray Group Jun 2003 - Present
    Preconstruction:Working with our preconstruction department, providing a key operation link in preparing the tender documents, attending meetings, developing methods of work, liaising with potential subcontractors and assisting were very required to secure new works.Operational:From award to delivery (Safely, on time and on budget) of many projects for the following clients;Milton Keynes Council, MaceDragados jv, Skanska, Bovis Lend Lease, Stanhope plc, Sir Robert McAlpine, Canary Wharf Contractors, Legal & General, MACE, British Land, The Crown Estate, Glaxo Smith Kline (GSK), Arab Investments, Heron, Grosvenor Estates, Berkeley Homes, Network Rail, Crossrail, BPSDC, CORE, OPLM.At the following contracts:The Gables & Melish Court Demolition, Chapter Living London Bridge, Maria Fidelis - Euston HS2, 20 Ropemaker Street, Battersea Power Station Phase 2, Battersea Power Station Phase 3a, Quadrant 4 (Q4) development (Piccadilly), Block W5 Regent Street, Battersea Power Station Marketing suite, 7 - 8 St James Square, Birmingham Gate Project, Farringdon East Ticket Hall, Project Phoenix, 10 - 12 Copthall Ave (Pocket Park), St Botolphs, Heron Tower, The Pinnacle, Ropemaker Place, St Giles (demo & Groundwork packages), Guildhall Accommodation Block, 60 Threadneedle Street, Bow Bells House, 200 Pentonville Road,1 Coleman Street, 35 Basinghall Ave, 16 Coleman Street, Colchester Garrison, White City, 77 Grosvenor Street, Spitalfields.
  • Keltbray
    Chapter Living - London Bridge
    Keltbray Apr 2022 - Jul 2022
    London Bridge
    Member of the Keltbray project team undertaking the Piling & Groundworks package for Mace. The packages include the following scope: Construction of 125 linear metre secant piles wall, preparation and construction of a 1600 x 1415mm concrete capping beam on the secant piled wall, bulk excavation with MOLA watching brief and 2 specific MOLA excavations to a depth of 3 metres below street level, construction of a low-level piling platform, construction of bearing piles (26 wet piles, and 44 dry piles), followed by the installation of temporary propping to the capping and final bulk excavation to the new basement level formation with concrete blinding.
  • Keltbray Group
    Battersea Power Station Phase Ii
    Keltbray Group Nov 2015 - Aug 2021
    Battersea Power Station
    Member of the Keltbray project team undertaking the façade retention and structural demolition to Battersea Power station Phase II. The works includes the following scope: Site investigations, Mini piling, Main piling, Sheet piling, Cofferdam excavations, Reinforces concrete foundations, Structural alterations, Structural demolition, Installation and management of circa 3,000 tonnes of temporary works to facilitate the structural demolition, Dismantle of existing façade temporary works, Salvage of existing listed items for restoration by others e.g. light sockets, radiators, staircases, old plant, gantry cranes etc. On completion of the main works the Keltbray team were instructed to facilitate and manage the removal of the lead paint from the retained existing steels, the opening up pockets (circa 3,000 locations) through the brick and concrete encasement to expose the existing steels for the connections between the new and old steel frames, the removal of the previously installed temporary works (4,000 tonnes) and the demolition through the existing facades for new openings (windows and doorways).
  • Keltbray Group
    20 Ropemaker Street
    Keltbray Group Feb 2019 - Jun 2021
    20 Ropemaker Street
    Member of the Keltbray project team undertaking the demolition of the existing structures (101 Finsbury Pavement, 19- 24 Ropemaker Street and 10 - 12 Finsbury Street) of varying heights down to existing basement slabs and the Enabling works package (Piling probing, Piling, Capping beam, Temporary works, Bulk excavation, Blinding to formation) to facilitate the new basement box construction.
  • Keltbray Group
    Quadrant 4 Development - Q4
    Keltbray Group Jun 2014 - Nov 2015
    Quadrant 4 Development, 11 - 12 Sherwood Street.
    Member of the Keltbray project team undertaking the following scope of works: Asbestos removal, Site investigations, Structural Alterations, Structural demolition, Soft strip, Mini piling, RC foundations, Installation and manage of temporary works to facilitate the structural alternations. Steel strengthen, Installation of new steel, Concrete topping to new metal decking, concrete repairs, placing of sand / cement screeds.
  • Keltbray Group
    Regent Street Block W5 Project
    Keltbray Group Mar 2013 - Jun 2014
    Regent Street, Block W5 (South)
    Member of the Keltbray project team undertaking the following scope of works: Asbestos Removal, Soft Strip, Tower crane erection, traditional tube and fitting scaffolding, Stone dismantle for storage and restoration, structural demolition, installation of facade retention temporary works, ground enabling works during and post superstructure demolition , underpinning, sheet piling, basement temporary works and excavations with the aid of a loading gantry.
  • Keltbray Group
    Battersea Power Station Marketing Suite
    Keltbray Group Oct 2012 - Feb 2013
    Battersea Power Station
    Pile enabling, CFA piling, ground works and superstructure concrete works for the Battersea Power Station Marketing Suite.
  • Keltbray Group
    7 - 8 St James Square Project
    Keltbray Group Mar 2012 - Oct 2012
    7 - 8 St James Square, London, Sw1Y 4Jh
    Member of the Keltbray Project team under taking the Sub structure demolition, pile enabling, piling, mini piling, underpinning, back propping, stage 1,2&3 basement propping, bulk excavation.
  • Keltbray Group
    Birmingham Gateway Project
    Keltbray Group Jan 2011 - Feb 2012
    Birmingham, United Kingdom
    Member of the Keltbray Project team under taking the demolition of Stephensons Tower and Podium structures, as part of the south development of BGP.
  • Keltbray Group
    Farringdon East Ticket Hall Enabling Package
    Keltbray Group Nov 2009 - Feb 2011
    Barbican Station, City Of London
    The enabling (demolition) works for the Crossrail scheme at Farringdon East Ticket Hall worksite involve the demolition of 10 buildings of varying sizes comprising of masonry, timber and concrete. With its location the worksite had many adjacent stakeholders and 4 main interfaces: LU Barbican Station, NWR Moorgate Spur, Historical Smithfield meat market and City of London.Keltbray were awarded the inaugural Crossrail Contractors & Designers Award for outstanding Health, Safety, Environmental and Quality work on the C209 Farringdon Demolition East Ticket Hall contract.
  • Keltbray Group
    Heron Tower Project
    Keltbray Group Jan 2008 - Jun 2009
    Heron Tower, Bishopsgate, City Of London
    To prepare the site for the new Heron tower development two existing 1960 tower blocks on the site were de- constructed utilising tower crane demolition , this was followed by an extensive pile enabling and temporary works activities. An advanced 12 month pre-construction period was used to develop the successful top down basement construction that allowed for the 3 new basement levels to be formed concurrently to the superstructure erection.
  • Keltbray Group
    Pocket Park, Copthall Ave
    Keltbray Group Dec 2008 - May 2009
    Copthall Avenue, City Of London
    The demolition of – Copthall Avenue formed part of the Drapers Garden development. The site was located in the center of the City Of London which presented many logistical challenges requiring progressive planning with other trades working in adjacent projects. The building consisted of a 6 storey concrete frame with a single basement. Permanent ties were installed to ensure the stability of the adjacent party wall structures which were retained.
  • Keltbray Group
    Project Phoenix, Ware
    Keltbray Group Jan 2009 - Mar 2009
    Ware, Hertfordshire
    The project involved the removal of contaminated ducting, soft strip and internal demolition within two existing building know as B3 and B4 on the Glaxo Smith Kline research facility in Ware Hertfordshire. The works were carried out whilst the research site remained operational with the works being interfaced with other construction and refurbishment operations being carried out concurrently on the site.
  • Keltbray Group
    St Giles Court
    Keltbray Group Jul 2006 - Mar 2008
    St Giles Court
    Following on from the successful stage 1 demolition works Keltbray negotiated the pile enabling and sub-structure works packages on the Central St Giles development for Stanhope. The substructure package commenced with pile probing works to a depth of 5m allowing for the installation of secant wall and bearing piles. Running concurrently to the pile enabling works was pile attendance & a sequenced archaeological excavation to specific areas of the site followed by temporary works installation and bulk excavation works.
  • Keltbray Group
    The Pinnacle, Bishopsgate
    Keltbray Group Mar 2006 - Mar 2008
    Bishopsgate, London
    Keltbray carried out the demolition and enabling package to facilitate the construction of the Pinnacle tower in the heart of the City. The existing site was made up of three existing structures, of which 38 Bishopsgate proved to be the most challenging resulting in extensive specialist cutting and craneage being utilised for its de construction. In conjunction to the de construction works an extensive enabling works package was carried out in advance of the piling and sub structure packages.
  • Keltbray Group
    Ropemaker Place, Ropemaker Street
    Keltbray Group Sep 2006 - Aug 2007
    Ropemaker Street, City Of London
    The project entailed the formation of the new basement structure for the Ropemaker Place office development on the edge of the City Of London for British Land. The project was successful due to pre-planning and co-ordination with both the piling and RC contractor which was carried out in as a pre construction phase. Extensive temporary works were installed in conjunction with the existing basement demolition to allow maximum area for the follow on blue sky dig and new RC basement and core formation.
  • Keltbray Group
    Bow Bells House
    Keltbray Group Mar 2006 - Feb 2007
    Bow Bells House
    The project consisted of taking down the eight-storey Bow Bells House adjacent to the historic St Mary-le-bow church as part of the new Stanhope redevelopment of the site. The works included asbestos removal and soft strip demolition followed by full structural demolition and an extensive temporary works and sub structure package of works.
  • Keltbray Group
    Guildhall Accommodation Project
    Keltbray Group Jun 2006 - Jan 2007
    Guildhall, City Of London
    Located in a busy part of the City of London the former Guildhall offices and library was consisted of a 7 storey steel framed structure. The package entailed an extensive asbestos removal, soft strip and structural demolition package that was carried out whilst the adjoining Corporation of London's Guildhall facility was in full operation.
  • Keltbray Group
    200 Pentonville Road
    Keltbray Group Sep 2005 - Jul 2006
    200 Pentonville Road
    The development site consisted of 2No. 20 storey 1970’s tower blocks located off of the Pentonville Road which were de clad and soft stripped to allow for extending and re-cladding under the new scheme and demolition of the top 2 storeys (plant rooms) allowing for further extension. The low level podium structures were demolished utilising large machines and the de-cladding works were carried out utilising tower crane de construction.
  • Keltbray Group
    35 Basinghall Street
    Keltbray Group Jan 2005 - Jun 2006
    35 Basinghall Street, London
    The building consisted of an 8 storey concrete frame 1960’s office building with a shared party wall to the Southern boundary. The initial works entailed the removal of asbestos based materials and de-commissioning of the existing services, this was followed by a soft strip operation and then full structural demolition. Structural demolition was carried out on a floor by floor basis using mini excavators & skid steers down to second floor. Down to second floor level where larger machines were then used to complete the demolition.
  • Keltbray Group
    1 Coleman Street (Austral House)
    Keltbray Group Dec 2004 - Jun 2006
    1 Coleman Street
    The Austral house project was carried out over a two stage approach with the first stage being a de-rating exercise consisting of asbestos removal and soft strip demolition. Stage 2 works on the project entailed the completion of soft stripping and the structural demolition of the existing 9 storey 1960’s office block followed on by an extensive pile enabling and basement excavation package.
  • Keltbray Group Holdings Ltd - St Giles Court Demolition
    St Giles Court - Demolition
    Keltbray Group Holdings Ltd - St Giles Court Demolition Aug 2005 - May 2006
    St Giles Court
    The Works entailed the Demolition of the existing 9 storey office buildings that formed the St Giles Court office complex at the Eastern end of Oxford Street in the West end of London. The demolition was carried out to make way for the 403,883 sq ft Central Saint Giles mixed residential and office development for Stanhope Plc. The works were carried out over 2 stages with an initial asbestos removal and de rating operation followed by a return visit to complete the structural demolition.
  • Keltbray Group Holdings Ltd
    Colchester Barracks Pfi Phases 1 & 2
    Keltbray Group Holdings Ltd Jan 2004 - Dec 2004
    Colchester, England, United Kingdom
    Colchester Barracks Phase 1 & 2 was a Joint venture with Lagan Group to provide the full enabling and infrastructure works for the new £600m PFI army barracks at Colchester for the Ministry of Defence. The project included both works on existing green field areas along with areas of the existing barracks, whilst maintaining full security and operational status for the live barracks site.
  • Keltbray Group Holdings Ltd
    Spitalfields Market - London
    Keltbray Group Holdings Ltd Jun 2003 - Jan 2004
    Spitalfields Market
    The project involved the demolition and groundworks to part of the old Spitalfields market on the edge of the City of London to make way for a new City office development for Hammerson. The project was carried out successfully despite the confined city centre location and tight programme constraints.
  • Bovis Lend Lease
    Construction Manager
    Bovis Lend Lease Apr 2002 - Apr 2003
    Block W8 - Regent Street (Apple'S London Flagship Store)
    The project was the first phase of Regent Street redevelopment in the heart of London’s west end. The site being adjacent to the busy Oxford Circus underground station and junction posed many logistical challenges.The existing site was made up of eleven structures of varying ages and forms of construction with a listed Georgian stone façade along the Regent Street elevation which had to be retained in the new scheme. The development provided high specification office and residential accommodation plus retail outlets at ground level to Regent Street, which includes the Apple flagship store.
  • Mcgee Group
    Project Manager
    Mcgee Group Jul 1989 - May 2002

Oliver Long Skills

Demolition Construction Project Planning Contractors Drainage Subcontracting Construction Management Asbestos Deep Foundations Project Delivery Procurement Project Management Commercial Management Refurbishing Groundworks Pre Construction Quantity Surveying Rail Contract Management Basements Temporary Works Planning And Installation Temporary Staffing Facade Retention Smsts Construction Safety Network Rail Cre Bulk Excavation Level 1 Football Coach Basement Excavation Project Estimation Project Bidding Cost Control

Oliver Long Education Details

  • Mace Business School
    Mace Business School
    Mciob Epa Programme
  • Institute Of Technology Tralee
    Institute Of Technology Tralee
    Construction Studies

Frequently Asked Questions about Oliver Long

What company does Oliver Long work for?

Oliver Long works for Keltbray Group

What is Oliver Long's role at the current company?

Oliver Long's current role is Operations Director.

What is Oliver Long's email address?

Oliver Long's email address is ol****@****ray.com

What schools did Oliver Long attend?

Oliver Long attended Mace Business School, Institute Of Technology Tralee.

What are some of Oliver Long's interests?

Oliver Long has interest in Football, Rugby, Formula 1, Football Coaching, Mountain Biking, Golf.

What skills is Oliver Long known for?

Oliver Long has skills like Demolition, Construction, Project Planning, Contractors, Drainage, Subcontracting, Construction Management, Asbestos, Deep Foundations, Project Delivery, Procurement, Project Management.

Not the Oliver Long you were looking for?

Free Chrome Extension

Find emails, phones & company data instantly

Find verified emails from LinkedIn profiles
Get direct phone numbers & mobile contacts
Access company data & employee information
Works directly on LinkedIn - no copy/paste needed
Get Chrome Extension - Free

Download 750 million emails and 100 million phone numbers

Access emails and phone numbers of over 750 million business users. Instantly download verified profiles using 20+ filters, including location, job title, company, function, and industry.