Sr.Planning Engineer
Current- Breakdown the Work Packages into smallest activities to establish the accurate level of planning.
- Develop the Level 4 Schedule for the project based on the approved level 3 Schedule and the engineering quantities with reference to Mhrs rates
- Develop schedule revisions to study the impact of the change in design issued by the Contractor on the original plan or any other decision that might reflect a delay on the original plan
- Maintains Program Master Schedule and performs critical path analysis including management of program to program interfaces and milestones.
- Develop the Path of Construction based on the Project milestones and logic se-quence of work.
- Develop the Heavy Lift Equipment schedule